Pipe-Lines

Aberdeen CityAB10 1BJ57.146042-2.107375Petroleum Act 19982020-11-032020-11-052020-11-102020-11-122020-11-132020-11-162020-11-182020-11-192020-11-202020-11-252020-11-262020-11-272020-11-302020-12-08TSO (The Stationery Office), customer.services@thegazette.co.uk369138663198

OFFSHORE PETROLEUM REGULATOR FOR ENVIRONMENT AND DECOMMISSIONING

THE OFFSHORE PETROLEUM PRODUCTION AND PIPE-LINES (ASSESSMENT OF ENVIRONMENTAL EFFECTS) REGULATIONS 1999 (AS AMENDED)

DIRECTION DECISIONS 

Pursuant to regulations 6(11) and 6(12) of the above Regulations, the Secretary of State gives notice of the following decision(s), in respect of application(s) made under regulation 6 of the above Regulations requesting a direction confirming that a relevant project need not be accompanied by an environmental statement and confirming the Secretary of State’s agreement to the grant of consent.

Reference Operator Project Name Quad/ Block Direction Issued
DRA/839 CNOOC Petroleum Europe Ltd Golden Eagle 20/01a BPG Infill Well 20/01 18/11/2020
DRA/814 Total E&P UK Ltd Elgin Wellhead Platform Development Well 22/30 27/11/2020
Main reasons / conclusions on which decision is based Main considerations related to marine discharges and atmospheric emissions. Discharges assessed as no risk to marine environment, and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant.
Mitigation features / measures Any cuttings contaminated with oil-based mud will be treated offshore prior to discharge or shipped to shore for treatment and disposal. Appropriate controls will be in place to reduce the likelihood of accidental events.
Reference Operator Project Name Quad/ Block Direction Issued
DRA/827 CNOOC Petroleum Europe Ltd Glengorm South Appraisal Well 22/26 12/11/2020
DRA/837 CNOOC Petroleum Europe Ltd Scott 15/22 – J25 Production Well 15/22 20/22/2020
Main reasons / conclusions on which decision is based Main considerations related to marine discharges, atmospheric emissions and interference with other users of the sea. Discharges assessed as no risk to marine environment and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant.
Mitigation features / measures Any cuttings contaminated with oil-based mud will be treated offshore prior to discharge or shipped to shore for treatment and disposal, and works will be undertaken in accordance with applicable navigational conditions.  Appropriate controls will be in place to reduce the likelihood of accidental events.
Reference Operator Project Name Quad/ Block Direction Issued
PRA/293 Zennor Pathway Ltd Finlaggan Field Commencement of Production 21/5 26/11/2020
Main reasons / conclusions on which decision is based Main considerations related to marine discharges and atmospheric emissions.  Discharges assessed as no risk to the environment and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant.
Mitigation features / measures Appropriate controls in place to reduce the likelihood of accidental events and agreement was given to the issue of consent, providing increases are as specified in the application.  
Reference Operator Project Name Quad/ Block Direction Issued
PRA/43 Apache Beryl I Ltd Garten Field Increase in Production 09/18 05/11/2020
PRA/84 Shell U.K. Ltd Corvette Field Increase in Production 49/24 10/11/2020
PRA/84 Shell U.K. Ltd Leman Field Increase in Production 49/26 12/11/2020
PRA/15 Total E&P UK Ltd Jura Field Increase in Production 03/09 13/11/2020
PRA/103 Spirit Energy Resources Ltd Grove Field Increase in Production 49/10 13/11/2020
PRA/254 Spirit North Sea Gas Ltd Ceres Field Increase in Production 47/9 13/11/2020
PRA/31 Perenco UK Ltd Ravenspurn North Increase in Production 43/27 3/11/2020
PRA/52 Shell U.K. Ltd Shearwater Field Increase in Production 22/30 16/11/2020
PRA/42 Dana Petroleum (E&P) Ltd Bittern Increase in Production 29/1 20/11/2020
PRA/42 Dana Petroleum (E&P) Ltd Guillemot North West Increase in Production 29/30 20/11/2020
PRA/42 Dana Petroleum (E&P) Ltd Clapham Increase in Production 21/24 20/11/2020
PRA/278 Equinor UK Ltd Barnacle Increase in Production 211/29 25/11/2020
PRA/42 Dana Petroleum (E&P) Ltd Clapham Increase in Production 21/30 19/11/2020
PRA/42 Dana Petroleum (E&P) Ltd Guillemot North West Increase in Production 21/30 19/11/2020
PRA/42 Dana Petroleum (E&P) Ltd Bittern Increase in Production 21/30 19/11/2020
PRA/42 Dana Petroleum (E&P) Ltd Guillemot West Increase in Production 21/30 26/11/2020
PRA/42 Dana Petroleum (E&P) Ltd Pict Increase in Production 21/30 26/11/2020
PRA/85 Perenco UK Ltd Trent Increase in Production 43/24 27/11/2020
PRA/29 Perenco UK Ltd Wollaston Increase in Production 42/28 27/11/2020
PRA/81 Spirit Energy Production UK Ltd Rhyl Field Increase in Production 110/02 30/11/2020
PRA/253 NEO Energy (SNS) Ltd Boa Increase in Production 9/15 30/11/2020
Main reasons / conclusions on which decision is based Main considerations related to marine discharges and atmospheric emissions.  Discharges assessed as no risk to the environment and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant.
Mitigation features / measures Appropriate controls in place to reduce the likelihood of accidental events and agreement was given to the issue of consent, providing increase is as specified in the application.

Having regard to the relevant application(s) for direction(s) submitted under the above Regulations, the Secretary of State has assessed the project(s) as not likely to have a significant effect on the environment and has given a direction that the application for consent under the Petroleum Act 1998 need not be accompanied by an environmental statement. The main reasons and considerations on which this decision is based are summarised above and have taken full account of the characteristics of the project, the environmental sensitivity of the areas likely to be affected by the project and the nature and significance of the potential impacts, as set out in Schedule 1 to the Regulations. 

Excluded Activities

Pursuant to regulation 5(10) of the above Regulations, the Secretary of State gives notice that, having regard to the matters set out in regulations 5(2) and/or 5(2A) and Schedule 1 to the Regulations, the Secretary of State has decided that the operations in respect of which consent is sought would not be likely to have a significant effect on the environment and accordingly no environmental statement need be prepared in respect of the relevant project.

Reference Operator Project Name Quad/ Block
EX-306-2020 BP Exploration Operating Company Ltd Schiehallion Pipeline Works 204/20
EX-307-2020 BP Exploration Operating Company Ltd Schiehallion Pipeline Works 204/20
EX-308-2020 BP Exploration Operating Company Ltd Loyal Pipeline Works 204/20
EX-309-2020 Dana Petroleum (E&P) Ltd Guillemot West Pipeline Works 21/29
EX-310-2020 Premier Oil UK Ltd Balmoral Pipeline Works 16/21
EX-311-2020 Chrysaor Resources (Irish Sea) Ltd Dalton Extension of Production Consent 110/2
EX-312-2020 ENI UK Ltd Hamilton East Extension of Production Consent 110/13
EX-313-2020 ENI UK Ltd Hamilton North Extension of Production Consent 110/13
EX-314-2020 Perenco UK Ltd Hoton Extension of Production Consent 48/7
EX-315-2020 Perenco UK Ltd Hyde Extension of Production Consent 48/6
EX-316-2020 Premier Oil E&P UK EU Ltd Johnston Extension of Production Consent 43/27
EX-317-2020 Taqa Bratani Ltd Morrone Extension of Production Consent 9/23
EX-318-2020 Perenco UK Ltd North Davy Extension of Production Consent 53/5
EX-319-2020 Enterprise Oil Ltd Pierce Extension of Production Consent 23/27
EX-320-2020 Repsol Sinopec Resources UK Ltd Ross Extension of Production Consent 13/28
EX-321-2020 Alpha Petroleum Resources Ltd Wenlock Extension of Production Consent 49/12
EX-322-2020 Perenco UK Limited West Sole Extension of Production Consent 48/6
EX-323-2020 Repsol Sinopec Resources UK Ltd Ross Extension of Production Consent 13/28
EX-324-2020 Wintershall Noordzee B.V. Wingate Extension of Production Consent 44/24
EX-325-2020 Spirit Energy Production UK Ltd Rhyl Extension of Production Consent 113/27
EX-326-2020 Shell U.K. Ltd Corvette Extension of Production Consent 49/24
EX-327-2020 Enquest Heather Ltd Don South West Extension of Production Consent 211/18
EX-328-2020 Enquest Heather Ltd West Don Extension of Production Consent 211/18
EX-329-2020 Enquest Heather Ltd Heather Extension of Production Consent 2/5
EX-330-2020 Repsol Sinopec Resources UK Ltd Leven Extension of Production Consent 30/17
EX-331-2020 BP Exploration & Operating Company Ltd Alligin Extension of Production Consent 204/20
EX-332-2020 Britoil Ltd Foinaven Extension of Production Consent 204/24

Further information in relation to all the decisions detailed in this notice can be found on the GOV.UK website at: 

  https://www.gov.uk/guidance/oil-and-gas-environmental-data.  

  If you have any questions in relation to this notice or the decisions, please contact the Environmental Management Team, Offshore Petroleum Regulator for Environment and Decommissioning (OPRED), AB1 Building, Crimon Place, Aberdeen AB10 1BJ (e-mail: emt@beis.gov.uk).