Transport Acts

Transport and Works Act 1992TRANSPORT AND WORKS ACT 19922015-12-152015-12-18The City of Westminster-0.13516451.497878SW1H 0TL-0.12930351.494637SW1P 4DRTSO (The Stationery Office), St Crispins, Duke Street, Norwich, NR3 1PD, 01603 622211, customer.services@tso.co.uk244986061442

Department for Transport

TRANSPORT AND WORKS ACT 1992

The Secretary of State for Transport gives notice under section 14(1)(b), (2A), (3A) and (3AA) of the Transport and Works Act 1992 (“the Act”) that he has determined under section 13(1) of the Act to make with modifications the London Underground (Bank Station Capacity Upgrade) Order (“the Order”).

The Order was applied for by London Underground Limited, Windsor House, 42-50 Victoria Street, London, SW1H 0TL. It will authorise the construction and operation of works at Bank Station in the City of London to create additional passenger access capacity to the Northern Line underground railway at that station. Copies of the Order, once made, may be obtained from the Stationery Office or through booksellers.

The Secretary of State has, under section 14(1)(a) of the Act, given notice of his determination by way of a decision letter dated 15 December 2015, copies of which may be obtained from the TWA Orders Unit, Department for Transport, Zone 1/14-18, Great Minster House, 33 Horseferry Road, London, SW1P 4DR. That letter gives the reasons for the determination and the considerations upon which it is based; information about the public participation process; and information regarding the right to challenge the validity of the determination and the procedures for doing so.

The Secretary of State confirms that, before making his determination, he considered the environmental statement provided by the applicant and all objections and other representations relating to it, and that he otherwise complied with the obligations referred to in section 14(3A) of the Act. For the purposes of section 14(3AA) of the Act, he confirms that the main measures to avoid, reduce and, if possible, remedy any major adverse environmental effects are those referred to in in paragraph 19 of the decision letter.

Martin Woods, Head of the TWA Orders Unit, Department for Transport, Zone 1/14-18, Great Minster House, 33 Horseferry Road, London SW1P 4DR.