Pipe-Lines
OFFSHORE PETROLEUM REGULATOR FOR ENVIRONMENT AND DECOMMISSIONING
THE OFFSHORE PETROLEUM PRODUCTION AND PIPE-LINES (ASSESSMENT OF ENVIRONMENTAL EFFECTS) REGULATIONS 1999 (AS AMENDED)
DIRECTION DECISIONS
Pursuant to regulations 6(11) and 6(12) of the above Regulations, the Secretary of State gives notice of the following decision(s), in respect of application(s) made under regulation 6 of the above Regulations requesting a direction confirming that a relevant project need not be accompanied by an environmental statement and confirming the Secretary of State’s agreement to the grant of consent.
Reference | Operator | Project Name | Quad/ Block | Direction Issued |
PLA/802 | Repsol Sinopec Resources UK Limited | Scapa Production Protection Project | 14/19 | 02/02/2021 |
Main reasons / conclusions on which decision is based | Main considerations related to deposit of materials on the seabed and marine discharges. Discharges assessed as no risk to the marine environment, and impacts assessed as localised and not significant. | |||
Mitigation features/measures | Deposits will be the minimum required to achieve objectives and appropriate controls will be in place to reduce the likelihood of accidental events. Agreement was given to the issue of consent providing works are undertaken as specified in the application. |
Further information in relation to all the decisions detailed in this notice can be found on the GOV.UK website at:
https://www.gov.uk/guidance/oil-and-gas-environmental-data.
If you have any questions in relation to this notice or the decisions, please contact the Environmental Management Team, Offshore Petroleum Regulator for Environment and Decommissioning (OPRED), AB1 Building, Crimon Place, Aberdeen AB10 1BJ (e-mail: emt@beis.gov.uk). .