Transport Acts

Transport and Works Act 1992Transport and Works Act 1992, s. 62017-05-182017-04-03The City and County of Cardiff-3.18267951.488786CF10 3NQ-0.13215751.528046NW1 2DNThe London Borough of Camden-3.17603851.475302CF10 5BTTSO (The Stationery Office), St Crispins, Duke Street, Norwich, NR3 1PD, 01603 622211, customer.services@tso.co.uk275156061891

The Transport and Works Act 1992

The Transport and Works (Applications and Objections Procedure) (England and Wales) Rules 2006

The Network Rail (Summerway Overbridge) Order

NOTICE OF APPLICATION FOR AN ORDER

Network Rail Infrastructure Limited (“Network Rail”) of 1 Eversholt Street, London NW1 2DN is applying to the Welsh Ministers under section 6 of the Transport and Works Act 1992 for the above-mentioned Order under sections 1 and 5 of that Act.

The Order would authorise Network Rail to extinguish public or private rights of way over the former occupation crossing known as the Summerway Overbridge (No. 133A) which is located on the South Wales Mainline in the City and County of Newport and for the temporary possession of land in connection with works required to demolish the Summerway Overbridge.

The application is not to be made subject to an environmental impact assessment.

Any objections to, or other representations about, the proposals in the application should be sent to the Welsh Ministers, Planning Decisions, Welsh Government, Cathays Park 2, Cardiff, CF10 3NQ (email: planning.directorate@wales.gsi.gov.uk).

An objection or other representation MUST (i) be received by the Welsh Ministers on or before 18 May 2017, (ii) be made in writing (whether sent by post or email), (iii) state the grounds of the objection or other representation, (iv) indicate who is making the objection or other representation, and (v) give an address to which correspondence relating to the objection or other representation may be sent. (If you are sending your objection or other representation by email, please provide a postal address and state “Summerway Overbridge TWA Order” in the subject of the email).

The Welsh Ministers may make complete copies of the objections and other representations public, including any personal information contained in them, and will copy them to the applicant for the Order.

Eversheds Sutherland (International) LLP, Solicitors and Parliamentary Agents, 1 Callaghan Square, Cardiff CF10 5BT.

On behalf of Network Rail Infrastructure Limited.

3 April 2017