Pipe-Lines

Petroleum Act 19982018-11-072019-02-062019-03-012019-03-042019-03-052019-03-082019-03-122019-03-142019-03-152019-03-182019-03-192019-03-202019-03-212019-03-222019-03-252019-03-282019-03-292019-04-05TSO (The Stationery Office), St Crispins, Duke Street, Norwich, NR3 1PD, 01603 622211, customer.services@tso.co.uk32510558144

THE OFFSHORE PETROLEUM PRODUCTION AND PIPE-LINES (ASSESSMENT OF ENVIRONMENTAL EFFECTS) REGULATIONS 1999 (AS AMENDED)

ENVIRONMENTAL STATEMENT DECISIONS

Pursuant to regulations 5A(7) and 5A(8) of the above Regulations, the Secretary of State gives notice of the following decision(s) in respect of the Secretary of State’s agreement to the grant of consent in relation to a relevant project under regulation 5A(1)(c) of the above Regulations.

Reference   Operator   Project Name   Quad/ Block   Decision Issued  
D/4225/2018 Premier Oil E&P UK Limited   Tolmount to Easington Pipeline ES 42/28d, 47/3i, 47/2c, 47/2d, 47/7, 47/6 & 47/11 29/03/2019
Summary of representations received   Consultees confirmed no objections and no representations were received in response to the public notice.  
Main reasons / conclusions on which decision is based   Main considerations related to physical presence, seabed disturbance, marine discharges, noise and atmospheric emissions, but impacts were assessed as localised and not significant. 
Relevant mitigation measures, environmental conditions or monitoring conditions attached to decision    Agreement to the issue of consent is conditional upon all works being undertaken as detailed in the Environmental Statement. Additional conditions attached relating to archaeological surveys, vessel movements in Special Protection Area, spoil tips and pipeline protection in Marine Conservation Zones.

Having regard to the Environmental Statement(s) submitted under the above Regulations, any information provided under regulation 10 of these Regulations and any representations received, the Secretary of State has assessed the project(s) as not likely to have a significant effect on the environment and has agreed to the grant of consent under the Petroleum Act 1998.

Direction Decisions

Pursuant to regulations 6(11) and 6(12) of the above Regulations, the Secretary of State gives notice of the following decision(s), in respect of application(s) made under regulation 6 of the above Regulations requesting a direction confirming that a relevant project need not be accompanied by an environmental statement and confirming the Secretary of State’s agreement to the grant of consent.

Reference Operator Project Name Quad/ Block Direction Issued
DRA/641 CNR International (U.K.) Ltd Rocksteady (S58zRD-E1z) 03/08 19/03/2019
DRA/637 Total E&P North Sea UK Ltd Culzean Well 22/25 22/03/2019
Main reasons / conclusions on which decision is based Main considerations related to marine discharges and atmospheric emissions. Discharges assessed as no risk to marine environment, and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant.
Mitigation features / measures Any cuttings contaminated with oil-based mud will be treated offshore prior to discharge or shipped to shore for treatment and disposal. Appropriate controls will be in place to reduce the likelihood of accidental events.
Reference Operator Project Name Quad/ Block Direction Issued
DRA/615 Chrysaor North Sea Ltd Mabel Appraisal Well 16/29 06/02/2019
DRA/628 Petrofac Facilities Management Ltd Blackrock Exploration Well 204/05 04/03/2019
DRA/661 Equinor UK Ltd Mariner AAMPI development well 09/11 01/03/2019
DRA/666 Equinor UK Ltd Mariner AMPJ development well 09/11 05/03/2019
DRA/667 Equinor UK Ltd Mariner AAMPB development well 09/11 14/03/2019
DRA/668 Equinor UK Ltd Mariner AMIC development well 09/11 12/03/2019
DRA/680 Equinor UK Ltd Mariner AMPO development well 09/11 15/03/2019
DRA/677 Apache North Sea Ltd Forties Delta Sidetrack well 21/10 20/03/2019
DRA/642 ConocoPhillips (U.K.) Ltd Brodgar HD development well 21/03 18/03/2019
DRA/674 Equinor UK Ltd Mariner AMPA development well 09/11 19/03/2019
DRA/675 Equinor UK Ltd Mariner AMPG development well 09/11 21/03/2019
DRA/676 Equinor UK Ltd Mariner ASA development well 09/11 25/03/2019
DRA/631 Ithaca Energy (UK) Ltd Cook Water Injection Well 21/20 08/03/2019
DRA/664 Ithaca Energy (UK) Ltd Stella Infill Well 30/06 28/03/2019
DRA/639 Total E&P North Sea UK Ltd Ballindalloch Well 09/19 01/03/2019
DRA/653 CNOOC Petroleum Europe Ltd Buzzard NIT development well 20/01 29/03/2019
DRA/669 CNOOC Petroleum Europe Ltd Buzzard NIC development well 20/01 29/03/2019
DRA/670 CNOOC Petroleum Europe Ltd Buzzard NT7 development well 20/01 29/03/2019
DRA/671 CNOOC Petroleum Europe Ltd Buzzard NT4A development well 20/01 29/03/2019
DRA/672 CNOOC Petroleum Europe Ltd Buzzard NP5 development well 20/01 29/03/2019
DRA/673 CNOOC Petroleum Europe Ltd Buzzard CPZ5 development well 20/01 29/03/2019
Main reasons / conclusions on which decision is based Main considerations related to marine discharges, atmospheric emissions and interference with other users of the sea. Discharges assessed as no risk to marine environment and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant.
Mitigation features / measures Any cuttings contaminated with oil-based mud will be treated offshore prior to discharge or shipped to shore for treatment and disposal, and works will be undertaken in accordance with applicable navigational conditions.  Appropriate controls will be in place to reduce the likelihood of accidental events.
Reference Operator Project Name Quad/Block Direction Issued
PLA/647 Eni Hewett Ltd Stabilisation of PL21 48/29 15/03/2019
PLA/652 Eni Hewett Ltd Stabilisation of PL20 48/29 15/03/2019
Main reasons / conclusions on which decision is based Main considerations related to deposit of materials on the seabed and interference with other users of the sea. Impacts assessed as localised and not significant.
Mitigation features / measures Deposits will be the minimum required to achieve objectives and designed to prevent unnecessary interference with other users of the sea. Works will be undertaken in accordance with applicable navigational conditions and appropriate controls will be in place to reduce the likelihood of accidental events. Agreement was given to the issue of consent providing works are undertaken as specified in the application.
Reference Operator Project Name Quad/Block Direction Issued
PLA/614 Shell U.K. Ltd Gannet Export Pipeline 30/11, 30/12 & 30/13 27/03/19
PLA/612 Shell U.K. Ltd Shearwater FGL Replumb 22/30, 29/5, 29/10 & 29/03 26/03/19
Main reasons / conclusions on which decision is based Main considerations related to installation of infrastructure and associated deposit of materials on the seabed, marine discharges and interference with other users of the sea.  Discharges assessed as no risk to the marine environment, and impacts assessed as localised and not significant.
Mitigation features / measures Deposits will be the minimum required to achieve objectives and designed to prevent unnecessary interference with other users of the sea. Works will be undertaken in accordance with applicable navigational conditions and appropriate controls will be in place to reduce the likelihood of accidental events. Agreement was given to the issue of consent providing works are undertaken as specified in the application.
Reference Operator Project Name Quad/Block Direction Issued
PRA/29 Perenco UK Ltd Minerva Increase in Production 47/03 20/03/2019
PRA/29 Perenco UK Ltd Wollaston Increase in Production 42/28 07/11/2018
Main reasons / conclusions on which decision is based Main considerations related to marine discharges and atmospheric emissions.  Discharges assessed as no risk to the environment and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant.
Mitigation features / measures Appropriate controls in place to reduce the likelihood of accidental events and agreement was given to the issue of consent, providing increase is as specified in the application.

Having regard to the relevant application(s) for direction(s) submitted under the above Regulations, the Secretary of State has assessed the project(s) as not likely to have a significant effect on the environment and has given a direction that the application for consent under the Petroleum Act 1998 need not be accompanied by an environmental statement. The main reasons and considerations on which this decision is based are summarised above and have taken full account of the characteristics of the project, the environmental sensitivity of the areas likely to be affected by the project and the nature and significance of the potential impacts, as set out in Schedule 1 to the Regulations.

Excluded Activities

Pursuant to regulation 5(10) of the above Regulations, the Secretary of State gives notice that, having regard to the matters set out in regulations 5(2) and/or 5(2A) and Schedule 1 to the Regulations, the Secretary of State has decided that the operations in respect of which consent is sought would not be likely to have a significant effect on the environment and accordingly no environmental statement need be prepared in respect of the relevant project.

Reference Operator Project Name Quad/ Block
EX-10-2019 Dana Petroleum (E&P) Ltd Saxon Field pipeline works 21/23

Further information in relation to all the decisions detailed in this notice can be found on the GOV.UK website at:

https://www.gov.uk/guidance/oil-and-gas-environmental-data.

If you have any questions in relation to this notice or the decisions, please contact the Environmental Management Team, Offshore Petroleum Regulator for Environment and Decommissioning (OPRED), AB1 Building, Crimon Place, Aberdeen AB10 1BJ (e-mail: emt@beis.gov.uk).