Pipe-Lines
THE OFFSHORE PETROLEUM PRODUCTION AND PIPE-LINES (ASSESSMENT OF ENVIRONMENTAL EFFECTS) REGULATIONS 1999 (AS AMENDED)
DIRECTION DECISIONS
Pursuant to regulations 6(11) and 6(12) of the above Regulations, the Secretary of State gives notice of the following decision(s), in respect of application(s) made under regulation 6 of the above Regulations requesting a direction confirming that a relevant project need not be accompanied by an environmental statement and confirming the Secretary of State’s agreement to the grant of consent.
Reference | Operator | Project Name | Quad/ Block | Direction Issued |
DRA/719 | Apache Beryl I Limited | 9/13a – B65Z Sidetracked development well | 09/13 | 08/08/2019 |
DRA/718 | CNOOC Petroleum Europe Ltd | Buzzard 20/06a-B2 Well | 20/06 | 08/08/2019 |
DRA/707 | TAQA Bratani Ltd | North Cormorant 211/21-N83 well | 211/21 | 05/08/2019 |
DRA/720 | CNR International (U.K.) Limited | Ninan South 3/08-s89 | 03/08 | 13/08/2019 |
DRA/724 | CNR International (U.K.) Limited | Ninian South 3/08-S75 | 03/08 | 29/08/2019 |
DRA/722 | Total E&P North Sea UK Ltd | Culzean 22/25a-C7 | 22/25 | 30/08/2019 |
Main reasons / conclusions on which decision is based | Main considerations related to marine discharges and atmospheric emissions. Discharges assessed as no risk to marine environment, and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant. | |||
Mitigation features / measures | Any cuttings contaminated with oil-based mud will be treated offshore prior to discharge or shipped to shore for treatment and disposal. Appropriate controls will be in place to reduce the likelihood of accidental events. |
Reference | Operator | Project Name | Quad/ Block | Direction Issued |
DRA/687 | Premier Oil E & P UK Limited | Tolmount E Appraisal Well | 42/28 | 31/07/2019 |
DRA/712 | Apache Beryl I Limited | 9/18a-41 Garten 2 Development Well | 9/18 | 01/08/2019 |
DRA/714 | Apache North Sea Limited | 21/10-A11 Forties A Sidetrack well | 21/10 | 01/08/2019 |
DRA/701 | Equinor UK Ltd | 22/10b - I Lifjellet Exploration Well | 22/10 | 09/08/2019 |
DRA/723 | Equinor UK Ltd | 211/30c - B33/12-B-29 A Barnacle Development Well | 211/30 | 15/08/2019 |
DRA/702 | BP Exploration Operating Co Ltd | Loyal Water Injection Well 204/20-L12 | 204/20 | 16/08/2019 |
DRA/703 | BP Exploration Operating Co Ltd | Loyal Water Injection Well 204/20-L13 | 204/20 | 16/08/2019 |
DRA/704 | BP Exploration Operating Co Ltd | Schiehallion Water Injection Well 204/20-C32 | 204/20 | 16/08/2019 |
DRA/711 | Petrofac Facilities Management Ltd | Liberator Appraisal Well 13/23c-LPt-02 | 13/23 | 19/08/2019 |
DRA/690 | CNOOC Petroleum Europe Ltd | Howick 206/21-A Exploration Well | 206/21 | 23/08/2019 |
DRA/732 | Shell U.K. Limited | Penguins C-UpDip Development Well | 211/13 | 20/08/2019 |
Main reasons / conclusions on which decision is based | Main considerations related to marine discharges, atmospheric emissions and interference with other users of the sea. Discharges assessed as no risk to marine environment and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant. | |||
Mitigation features / measures | Any cuttings contaminated with oil-based mud will be treated offshore prior to discharge or shipped to shore for treatment and disposal, and works will be undertaken in accordance with applicable navigational conditions. Appropriate controls will be in place to reduce the likelihood of accidental events. |
Reference | Operator | Project Name | Quad/ Block | Direction Issued |
PLA/690 | Britoil Ltd | Foinaven Anode Skids Installation | 204/24 | 13/08/2019 |
Main reasons / conclusions on which decision is based | Main considerations related to deposit of materials on the seabed and interference with other users of the sea. Impacts assessed as localised and not significant. | |||
Mitigation features / measures | Deposits will be the minimum required to achieve objectives and designed to prevent unnecessary interference with other users of the sea. Works will be undertaken in accordance with applicable navigational conditions and appropriate controls will be in place to reduce the likelihood of accidental events. Agreement was given to the issue of consent providing works are undertaken as specified in the application. |
Reference | Operator | Project Name | Quad/ Block | Direction Issued |
PLA/686 | BP Exploration Operating Co Ltd | Glen Lyon PLU4719 Installation | 204/24 | 06/08/2019 |
Main reasons / conclusions on which decision is based | Main considerations related to installation of infrastructure and associated deposit of materials on the seabed, and interference with other users of the sea. Impacts assessed as localised and not significant. | |||
Mitigation features / measures | Deposits will be the minimum required to achieve objectives and designed to prevent unnecessary interference with other users of the sea. Works will be undertaken in accordance with applicable navigational conditions and appropriate controls will be in place to reduce the likelihood of accidental events. Agreement was given to the issue of consent providing works are undertaken as specified in the application. |
Reference | Operator | Project Name | Quad/ Block | Direction Issued |
PRA/39 | Shell U.K. Ltd | Penguins East | 211/13 | 07/08/2019 |
PRA/39 | Shell U.K. Ltd | Penguins West | 211/13 | 07/08/2019 |
PRA/25 | Spirit Energy Production UK Limited | South Morecambe | 110/03 | 21/08/2019 |
PRA/81 | Spirit Energy Production UK Limited | North Morecambe | 110/02 | 21/08/2019 |
PRA/45 | Apache North Sea Limited | Maule Field | 21/10 | 28/08/2019 |
PRA/43 | Apache Beryl I Limited | Ness Field | 09/13 | 28/08/2019 |
PRA/43 | Apache Beryl I Limited | Buckland Field | 09/13 | 28/08/2019 |
PRA/93 | Apache North Sea Limited | Tonto Field | 21/10 | 28/08/2019 |
PRA/45 | Apache North Sea Limited | Forties Field | 21/10 | 28/08/2019 |
Main reasons / conclusions on which decision is based | Main considerations related to marine discharges and atmospheric emissions. Discharges assessed as no risk to the environment and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant. | |||
Mitigation features / measures | Appropriate controls in place to reduce the likelihood of accidental events and agreement was given to the issue of consent, providing increase is as specified in the application. |
Having regard to the relevant application(s) for direction(s) submitted under the above Regulations, the Secretary of State has assessed the project(s) as not likely to have a significant effect on the environment and has given a direction that the application for consent under the Petroleum Act 1998 need not be accompanied by an environmental statement. The main reasons and considerations on which this decision is based are summarised above and have taken full account of the characteristics of the project, the environmental sensitivity of the areas likely to be affected by the project and the nature and significance of the potential impacts, as set out in Schedule 1 to the Regulations.
Excluded Activities
Pursuant to regulation 5(10) of the above Regulations, the Secretary of State gives notice that, having regard to the matters set out in regulations 5(2) and/or 5(2A) and Schedule 1 to the Regulations, the Secretary of State has decided that the operations in respect of which consent is sought would not be likely to have a significant effect on the environment and accordingly no environmental statement need be prepared in respect of the relevant project.
Reference | Operator | Project Name | Quad/ Block | Direction Issued |
EX-56-2019 | CNOOC Petroleum Europe Ltd | Buzzard Water Injection Manifolds Jumper Installation | 20/1 & 20/6 | 02/08/2019 |
EX-57-2019 | BP Exploration Operating Co Ltd | Schiehallion Central Jumper Installation | 204/20 | 05/08/2019 |
EX-58-2019 | EnQuest Heather Ltd | Goosander Electrical Flying Leads installation | 21/12 | 28/08/2019 |
EX-60-2019 | Equinor UK Limited | Mariner Production Increase Extension | 09/11 | 13/08/2019 |
EX-61-2019 | Chevron North Sea Limited | Alder Development Project. Replacement of umbilical tree jumper | 15/29 | 20/08/2019 |
Further information in relation to all the decisions detailed in this notice can be found on the GOV.UK website at:
https://www.gov.uk/guidance/oil-and-gas-environmental-data.
If you have any questions in relation to this notice or the decisions, please contact the Environmental Management Team, Offshore Petroleum Regulator for Environment and Decommissioning (OPRED), AB1 Building, Crimon Place, Aberdeen AB10 1BJ (e-mail: emt@beis.gov.uk).