Pipe-Lines
THE OFFSHORE PETROLEUM PRODUCTION AND PIPE-LINES (ASSESSMENT OF ENVIRONMENTAL EFFECTS) REGULATIONS 1999 (AS AMENDED)
DIRECTION DECISIONS
Pursuant to regulations 6(11) and 6(12) of the above Regulations, the Secretary of State gives notice of the following decision(s), in respect of application(s) made under regulation 6 of the above Regulations requesting a direction confirming that a relevant project need not be accompanied by an environmental statement and confirming the Secretary of State’s agreement to the grant of consent.
Reference | Operator | Project Name | Quad/ Block | Direction Issued |
DRA/726 | CNOOC Petroleum Europe Ltd | Scott ST-79 Production Well | 15/22 | 01/10/2019 |
DRA/737 | EnQuest Heather Ltd | Magnus M38 production well | 211/12 | 10/10/2019 |
DRA/747 | CNR International (U.K.) Ltd | Ninian South 3/08-S93RD - T-Bag Well | 03/08 | 10/10/2019 |
DRA/736 | EnQuest Heather Ltd | Magnus M49 production well | 211/12 | 18/10/2019 |
DRA/734 | Apache North Sea Ltd | Forties Development Well | 21/10-A57X | 10/10/2019 |
Main reasons / conclusions on which decision is based | Main considerations related to marine discharges and atmospheric emissions. Discharges assessed as no risk to marine environment, and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant. | |||
Mitigation features / measures | Any cuttings contaminated with oil-based mud will be treated offshore prior to discharge or shipped to shore for treatment and disposal. Appropriate controls will be in place to reduce the likelihood of accidental events. |
Reference | Operator | Project Name | Quad/ Block | Direction Issued |
DRA/619 | Rockrose UKCS8 LLC | West Brae Well- WPGZ | 16/07 | 03/10/2019 |
DRA/735 | Petrofac Facilities Management Ltd | Serenity Appraisal Well SA-01 | 13/23 | 04/10/2019 |
DRA/713 | Equinor UK Ltd | Frigg Appraisal Well | 10/01 | 10/10/2019 |
DRA/739 | Shell U.K. Ltd | Fram G5 Development Well | 29/03 | 29/10/2019 |
DRA/728 | Spirit Energy North Sea Ltd | Chiswick 49/04-C4 | 49/04 | 01/10/2019 |
DRA/739 | Shell U.K. Ltd | Fram G5 Development Well | 29/03 | 31/10/2019 |
Main reasons / conclusions on which decision is based | Main considerations related to marine discharges, atmospheric emissions and interference with other users of the sea. Discharges assessed as no risk to marine environment and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant. | |||
Mitigation features / measures | Any cuttings contaminated with oil-based mud will be treated offshore prior to discharge or shipped to shore for treatment and disposal, and works will be undertaken in accordance with applicable navigational conditions. Appropriate controls will be in place to reduce the likelihood of accidental events. |
Reference | Operator | Project Name | Quad/ Block | Direction Issued |
PLA/704 | Apache Beryl I Ltd | Pipeline PL725 | 09/19 | 03/10/2019 |
Main reasons / conclusions on which decision is based | Main considerations related to deposit of materials on the seabed and marine discharges. Discharges assessed as no risk to the marine environment, and impacts assessed as localised and not significant. | |||
Mitigation features/measures | Deposits will be the minimum required to achieve objectives and appropriate controls will be in place to reduce the likelihood of accidental events. Agreement was given to the issue of consent providing works are undertaken as specified in the application. |
Reference | Operator | Project Name | Quad/ Block | Direction Issued |
PRA/155 | BP Exploration Operating Co Ltd | Alligin Field Commencement of Production | 204/19 | 31/10/2019 |
Main reasons / conclusions on which decision is based | Main considerations related to marine discharges and atmospheric emissions. Discharges assessed as no risk to the environment and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant. | |||
Mitigation features/measures | Appropriate controls in place to reduce the likelihood of accidental events and agreement was given to the issue of consent, providing increases are as specified in the application. |
Reference | Operator | Project Name | Quad/Block | Direction Issued |
PRA/41 | CNR International UK | Columba E Field Increase in Production | 03/08 | 27/09/2019 |
PRA/126 | Repsol Sinopec Resources UK Ltd | Carnoustie field Increase in Production | 22/17 | 04/10/2019 |
PRA/15 | Total E&P UK Ltd | Nuggets N2 Field Increase in Production | 03/19 | 10/10/2019 |
PRA/15 | Total E&P UK Ltd | Nuggets N3 Field Increase in Production | 03/19 | 10/10/2019 |
PRA/15 | Total E&P UK Ltd | Ellon Field Increase in Production | 03/15 | 10/10/2019 |
PRA/15 | Total E&P UK Ltd | Jura Field Increase in Production | 03/15 | 10/10/2019 |
PRA/45 | Apache North Sea Ltd | Bacchus Field Increase in Production | 21/10 | 11/10/2019 |
PRA/46 | Repsol Sinopec Resources UK Ltd | Montrose Field Increase in Production | 22/17 | 15/10/2019 |
PRA/232 | Petrofac Facilities Management Ltd | Crathes Field increase in Production | 21/13 | 18/10/2019 |
PRA/84 | Shell U.K. Ltd | Corvette Field Increase in Production | 49/24 | 21/10/2019 |
PRA/232 | Petrofac Facilities Management Ltd | Scolty Field Increase in Production | 21/08 | 22/10/2019 |
PRA/143 | BP Exploration Operating Co Ltd | Mungo Field Increase in Production | 22/20 | 16/10/2019 |
PRA/32 | CNOOC Petroleum Europe Ltd | Scott Field Increase in Production | 15/22 | 24/10/2019 |
PRA/143 | BP Exploration Operating Co Ltd | Machar Field Increase in Production | 23/26 | 28/10/2019 |
PRA/102 | Total E&P North Sea UK Ltd | Global Producer III Production Increase | 15/20 | 04/10/2019 |
PRA/210 | Total E&P North Sea UK Ltd | Culzean Production Increase | 22/25 | 17/10/2019 |
PRA/41 | CNR International (U.K.) Ltd | Ninian Southern Platform Production Increase | 03/08 | 03/10/2019 |
PRA/12 | Total E&P North Sea UK Ltd | Gryphon A Production Increase | 09/18 | 14/10/2019 |
PRA/42 | Dana Petroleum (E&P) Ltd | Guillemot North West | 21/30 | 03/10/2019 |
Main reasons / conclusions on which decision is based | Main considerations related to marine discharges and atmospheric emissions. Discharges assessed as no risk to the environment and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant. | |||
Mitigation features / measures | Appropriate controls in place to reduce the likelihood of accidental events and agreement was given to the issue of consent, providing increase is as specified in the application. |
Having regard to the relevant application(s) for direction(s) submitted under the above Regulations, the Secretary of State has assessed the project(s) as not likely to have a significant effect on the environment and has given a direction that the application for consent under the Petroleum Act 1998 need not be accompanied by an environmental statement. The main reasons and considerations on which this decision is based are summarised above and have taken full account of the characteristics of the project, the environmental sensitivity of the areas likely to be affected by the project and the nature and significance of the potential impacts, as set out in Schedule 1 to the Regulations.
Excluded Activities
Pursuant to regulation 5(10) of the above Regulations, the Secretary of State gives notice that, having regard to the matters set out in regulations 5(2) and/or 5(2A) and Schedule 1 to the Regulations, the Secretary of State has decided that the operations in respect of which consent is sought would not be likely to have a significant effect on the environment and accordingly no environmental statement need be prepared in respect of the relevant project.
Reference | Operator | Project Name | Quad/ Block |
EX-67-2019 | CNOOC Petroleum Europe Ltd | Scott PL823 Pipeline Works | 15/22 |
EX-72-2019 | Shell U.K. Ltd | Brent PWA Exclusion | 211/29 |
EX-73-2019 | Perenco UK Ltd | Juno Whittle deposit of materials | 44/28 |
EX-74-2019 | Apache Beryl I Ltd | Garten 2 Well Tie-in | 09/18 |
EX-75-2019 | Chrysaor Petroleum Company U.K. Ltd | Joanne M11 well CIV1 LP hydraulic control line replacement | 30/07 |
EX-76-2019 | Chrysaor North Sea Ltd | Maria PLU2349 pipeline works | 16/29 |
EX-77-2019 | Serica Energy UK Ltd | Bruce pig launcher decommissioning | 09/08 |
EX-79-2019 | Spirit Energy Resources Ltd | Seven Seas Production Extension | 48/07 |
EX-80-2019 | Repsol Sinopec Resources UK Ltd | Tweedsmuir Production Extension | 21/01 |
EX-81-2019 | Repsol Sinopec Resources UK Ltd | Tweedsmuir South Production Extension | 21/01 |
EX-82-2019 | Tailwind Mistral Ltd | Gannet E Production Extension | 21/30 |
EX-83-2019 | CNR International (U.K.) Ltd | Banff Production Extension | 29/02 |
EX-84-2019 | Repsol Sinopec Resources UK Ltd | Burghley Production Extension | 16/22 |
EX-85-2019 | Alpha Petroleum Resources Ltd | Helvellyn Production Extension | 47/10 |
EX-86-2019 | Total E&P UK Ltd | Nuggets N3 Production Extension | 03/19 |
EX-87-2019 | Total E&P UK Ltd | Nuggets N2 Production Extension | 03/19 |
EX-88-2019 | Perenco UK Ltd | Cleeton Production Extension | 42/29 |
EX-89-2019 | Perenco UK Ltd | Woollaston Production Extension | 42/28 |
EX-90-2019 | Perenco UK Ltd | Whittle Production Extension | 48/28 |
EX-91-2019 | Perenco UK Ltd | Newsham Production Extension | 48/6 |
EX-92-2019 | Repsol Sinopec Resources UK Ltd | Arbroath Production Extension | 22/17 |
EX-93-2019 | Repsol Sinopec Resources UK Ltd | Arkwright Production Extension | 22/23 |
EX-94-2019 | Repsol Sinopec Resources UK Ltd | Auk Production Extension | 30/16 |
EX-95-2019 | Premier Oil UK Ltd | Balmoral Production Extension | 16/21 |
EX-96-2019 | Repsol Sinopec Resources UK Ltd | Beauly Production Extension | 09/13 |
EX-97-2019 | Apache Beryl I Ltd | Beryl Production Extension | 09/13 |
EX-98-2019 | Repsol Sinopec North Sea Ltd | Blake Production Extension | 13/24 |
EX-99-2019 | Repsol Sinopec Resources UK Ltd | Blane Production Extension | 30/03 |
EX-100-2019 | Verus Petroleum (SNS) Ltd | Boa Production Extension | 09/15 |
EX-101-2019 | Repsol Sinopec Resources UK Ltd | Brechin Production Extension | 22/23 |
EX-102-2019 | Shell U.K. Ltd | Brent Production Extension | 211/29 |
EX-103-2019 | Apache Beryl I Ltd | Callater Production Extension | 09/19 |
EX-104-2019 | Repsol Sinopec Resources UK Ltd | Cayley Production Extension | 22/17 |
EX-105-2019 | Taqa Bratani Ltd | Cladhan Production Extension | 210/29 |
EX-106-2019 | ENI UK Ltd | Douglas West Production Extension | 110/13 |
EX-107-2019 | Total E&P UK Ltd | Ellon Production Extension | 03/15 |
EX-108-2019 | Total E&P UK Ltd | Flyndre Production Extension | 30/14 |
EX-109-2019 | Repsol Sinopec Resources UK Ltd | Godwin Production Extension | 22/17 |
EX-110-2019 | ENI UK Ltd | Hamilton East Production Extension | 110/13 |
EX-111-2019 | Total E&P UK Ltd | Jura Production Extension | 03/15 |
EX-112-2019 | Apache Beryl I Ltd | Loirston Production Extension | 09/13 |
EX-113-2019 | Apache Beryl I Ltd | Nevis Production Extension | 9/13 |
EX-114-2019 | Repsol Sinopec Resources UK Ltd | Ross Production Extension | 13/28 |
EX-115-2019 | Repsol Sinopec Resources UK Ltd | Shaw Production Extension | 22/22 |
EX-116-2019 | Apache Beryl I Ltd | Skene Production Extension | 09/18 |
EX-117-2019 | Perenco UK Ltd | Wood Production Extension | 22/18 |
EX-118-2019 | Apache Beryl I Ltd | Garten Production Extension | 09/18 |
EX-119-2019 | Apache Beryl I Ltd | Ness Production Extension | 09/13 |
EX-120-2019 | Perenco UK Ltd | Amethyst East Production Extension | 47/14 |
EX-121-2019 | Perenco UK Ltd | Amethyst West Production Extension | 47/14 |
EX-122-2019 | Perenco UK Ltd | Davy East Production Extension | 53/05 |
EX-123-2019 | Dana Petroleum (E&P) Ltd | Saxon Production Extension | 21/23 |
EX-124-2019 | Shell U.K. Ltd | Pierce Production Extension | 23/27 |
EX-125-2019 | Apache Beryl I Ltd | Aviat Production Extension | 22/07 |
Further information in relation to all the decisions detailed in this notice can be found on the GOV.UK website at:
https://www.gov.uk/guidance/oil-and-gas-environmental-data.
If you have any questions in relation to this notice or the decisions, please contact the Environmental Management Team, Offshore Petroleum Regulator for Environment and Decommissioning (OPRED), AB1 Building, Crimon Place, Aberdeen AB10 1BJ (e-mail: emt@beis.gov.uk).