Pipe-Lines

Petroleum Act 19982020-07-022020-07-072020-07-102020-07-202020-07-212020-07-232020-07-272020-07-282020-07-302020-07-312020-08-062020-08-07TSO (The Stationery Office), customer.services@thegazette.co.uk36093468285

Offshore Petroleum Regulator for Environment and Decommissioning

THE OFFSHORE PETROLEUM PRODUCTION AND PIPE-LINES (ASSESSMENT OF ENVIRONMENTAL EFFECTS) REGULATIONS 1999 (AS AMENDED)

DIRECTION DECISIONS

Pursuant to regulations 6(11) and 6(12) of the above Regulations, the Secretary of State gives notice of the following decision(s), in respect of application(s) made under regulation 6 of the above Regulations requesting a direction confirming that a relevant project need not be accompanied by an environmental statement and confirming the Secretary of State’s agreement to the grant of consent.

Reference Operator Project Name Quad/ Block Direction Issued
DRA/815 CNOOC Petroleum Europe Ltd Golden Eagle Infill Well 20/01a - BPF 20/01 10/07/2020
DRA/820 Equinor UK Ltd Mariner 9/11a-AC40 Planned Well 9/11 27/07/2020
DRA/821 Equinor UK Ltd Mariner 9/11a-AC44 Planned Well 9/11 27/07/2020
DRA/826 APACHE BERYL I Ltd Beryl Alpha Well 9/13a-A42 9/13 28/07/2020
DRA/809 Shell U.K. Ltd Shearwater A17 Development Well 22/30 30/07/2020
Main reasons / conclusions on which decision is based Main considerations related to marine discharges and atmospheric emissions. Discharges assessed as no risk to marine environment, and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant.
Mitigation features / measures Any cuttings contaminated with oil-based mud will be treated offshore prior to discharge or shipped to shore for treatment and disposal. Appropriate controls will be in place to reduce the likelihood of accidental events.
Reference Operator Project Name Quad/ Block Direction Issued
DRA/819 APACHE BERYL I Ltd Gamma Pilot Planned Well 9/19 23/07/2020
Main reasons / conclusions on which decision is based Main considerations related to marine discharges, atmospheric emissions and interference with other users of the sea. Discharges assessed as no risk to marine environment and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant.
Mitigation features / measures Any cuttings contaminated with oil-based mud will be treated offshore prior to discharge or shipped to shore for treatment and disposal, and works will be undertaken in accordance with applicable navigational conditions. Appropriate controls will be in place to reduce the likelihood of accidental events.
Reference Operator Project Name Quad/Block Direction Issued
PLA/766 Neptune E & P UK Ltd Cygnus Pipeline Span Rectification 44/12 31/07/2020
Main reasons / conclusions on which decision is based Main considerations related to deposit of materials on the seabed and interference with other users of the sea. Impacts assessed as localised and not significant.
Mitigation features / measures Deposits will be the minimum required to achieve objectives and designed to prevent unnecessary interference with other users of the sea. Works will be undertaken in accordance with applicable navigational conditions and appropriate controls will be in place to reduce the likelihood of accidental events. Agreement was given to the issue of consent providing works are undertaken as specified in the application.
Reference Operator Project Name Quad/Block Direction Issued
PLA/743 BP Exploration Operating Company Ltd Schiehallion and Loyal Water Injection Expansion 204/20 02/07/2020
Main reasons / conclusions on which decision is based Main considerations related to installation of infrastructure and associated deposit of materials on the seabed, and marine discharges. Discharges assessed as no risk to the marine environment, and impacts assessed as localised and not significant.
Mitigation features / measures Deposits will be the minimum required to achieve objectives and appropriate controls will be in place to reduce the likelihood of accidental events. Agreement was given to the issue of consent providing works are undertaken as specified in the application.
Reference Operator Project Name Quad/Block Direction Issued
PLA/688 Shell U.K. Ltd Pierce Depressurisation Project 23/22 20/07/2020
Main reasons / conclusions on which decision is based Main considerations related to installation of infrastructure and associated deposit of materials on the seabed, marine discharges and interference with other users of the sea. Discharges assessed as no risk to the marine environment, and impacts assessed as localised and not significant.
Mitigation features / measures Deposits will be the minimum required to achieve objectives and designed to prevent unnecessary interference with other users of the sea. Works will be undertaken in accordance with applicable navigational conditions and appropriate controls will be in place to reduce the likelihood of accidental events. Agreement was given to the issue of consent providing works are undertaken as specified in the application.
Reference Operator Project Name Quad/Block Direction Issued
PRA/16 CNR International (U.K.) Ltd Toni Field Increase in Production 16/17 07/07/2020
PRA/66 CNR International (U.K.) Ltd Strathspey Field Increase in Production 3/4 07/07/2020
PRA/39 Shell U.K. Ltd Brent C Field Increase in Production 211/29 21/07/2020
PRA/52 Shell U.K. Ltd Shearwater Field Increase in Production 22/30 31/07/2020
Main reasons / conclusions on which decision is based Main considerations related to marine discharges and atmospheric emissions. Discharges assessed as no risk to the environment and atmospheric emissions rapidly dispersed to background levels. Impacts assessed as localised and not significant.
Mitigation features / measures Appropriate controls in place to reduce the likelihood of accidental events and agreement was given to the issue of consent, providing increase is as specified in the application.

Having regard to the relevant application(s) for direction(s) submitted under the above Regulations, the Secretary of State has assessed the project(s) as not likely to have a significant effect on the environment and has given a direction that the application for consent under the Petroleum Act 1998 need not be accompanied by an environmental statement. The main reasons and considerations on which this decision is based are summarised above and have taken full account of the characteristics of the project, the environmental sensitivity of the areas likely to be affected by the project and the nature and significance of the potential impacts, as set out in Schedule 1 to the Regulations.

Excluded Activities

Pursuant to regulation 5(10) of the above Regulations, the Secretary of State gives notice that, having regard to the matters set out in regulations 5(2) and/or 5(2A) and Schedule 1 to the Regulations, the Secretary of State has decided that the operations in respect of which consent is sought would not be likely to have a significant effect on the environment and accordingly no environmental statement need be prepared in respect of the relevant project.

Reference Operator Project Name Quad/ Block
EX-219-2020 Shell U.K. Ltd Gannet A Pipeline Works 21/25
EX-220-2020 EnQuest Heather Ltd Kraken Pipeline Works 9/2
EX-222-2020 Perenco UK Ltd Indefatigable Field Extension of Production Consent 49/23
EX-221-2020 Perenco UK Ltd Leman Field Extension of Production Consent 49/27
EX-223-2020 BP Exploration Operating Company Ltd Mirren Field Extension of Production Consent 42/29

Further information in relation to all the decisions detailed in this notice can be found on the GOV.UK website at:

https://www.gov.uk/guidance/oil-and-gas-environmental-data.

If you have any questions in relation to this notice or the decisions, please contact the Environmental Management Team, Offshore Petroleum Regulator for Environment and Decommissioning (OPRED), AB1 Building, Crimon Place, Aberdeen AB10 1BJ (e-mail: emt@beis.gov.uk).