Electricity
INVITATION TO PUBLIC CONSULTATION ON TROSTON 132 KV OVERHEAD LINE GRID CONNECTION PROPOSAL
SPEN invite you to a face-to-face public exhibition for the proposed Troston Overhead Line Grid Connection
SP Energy Networks is proposing to connect the Troston Loch Wind Farm to the national grid via an overhead line. If consented, the wind farm grid connection will be located in Dumfries and Galloway, about 6.2 km north-east of St John’s Town of Dalry and 10.4 km south-west of Moniaive.
Following our initial consultation on potential route options in 2022, a preferred route was taken forward for detailed design and environmental assessment. Information on the proposed overhead line and the Environmental Appraisal Report will be available from our website. We would like to invite everyone to view the information on our website as well as attend a public consultation event on 12 June 2024.
EXHIBITION
Dalry Town Hall,
St John's Town of Dalry, Castle Douglas
DG7 3SW
Wednesday 12 June 2024, 3-7pm
ONLINE INFORMATION
Further information about the proposal, public consultation materials and a feedback form is also available on the project website
http://www.spenergynetworks.co.uk/pages/troston_loch_wind_farm_connection.aspx
Anyone wishing to request information or comment on the proposed development may do so from 10 June to 1 July 2024 by completing an online feedback form/questionnaire to be made available on the website (above) or, alternatively, by telephone on 07516 461129; post to Troston Overhead Line Grid Connection Project, Land and Planning Team, SP Energy Networks, 55 Fullarton Drive, Glasgow G32 8FA; or email to trostonprojectmanager@spenergynetworks.co.uk